Electrical assembly on Unit 1,2,3 and 4
in TPP “ENEL Maritsa East” 3
- CONTRACTOR
- Siemens
- DATE
- 2006-2009
- PROJECT ACCEPTED BY
- Jens Grunwald, Oliver Sawodni

Participation in the complete rehabilitation of Unit 1, 2, 3 and 4 in part – Control Measurement Systems. Assembling cable traces, pulling and connecting cables, building frames and mounting connection boxes.
CONTRACTOR
Siemens
DATE
2006-2009
PROJECT ACCEPTED BY
Jens Grunwald, Oliver Sawodni
CONTRACTORS’ EVALUATION
The project is completed according to the assignment without any remarks.
- CONTRACTORS' EVALUATION
- The project is completed according to the assignment without any remarks.