Production and delivery of Supporting Bracket
TPP AES "Marica east 1" Galabovo
- CONTRACTOR
- Алстом
- DATE
- 2010
- PROJECT ACCEPTED BY
- Zornitsa Koleva
Production and delivery of 14pcs. Supporting Brackets for Unit 1 and Unit 2 in TPP AES “Marica east 1”, Galabovo.
CONTRACTOR
Alstom
DATE
2010
PROJECT ACCEPTED BY
Zornitsa Koleva
CONTRACTORS’ EVALUATION
The project is completed according to the assignment without any remarks.
- CONTACTOR'S EVALUATION
- The project is completed according to the assignment without any remarks.