Electrical assembly
in TPP “Agius Dmitrius”, Greece
- CONTRACTOR
- Siemens
- DATE
- April 2008
- PROJECT ACCEPTED BY
- Lutz Grossman

Pulling of control and power cables from turbine to the inner cabinet under command room.
CONTRACTOR
Siemens
DATE
April 2008
PROJECT ACCEPTED BY
Lutz Grossman
CONTRACTORS’ EVALUATION
The project is completed according to the assignment without any remarks.
- CONTRACTORS' EVALUATION
- The project is completed according to the assignment without any remarks.