Modification of Hydrogen analyzer system on all Units
in TPP "ENEL Maritsa East” 3
- CONTRACTOR
- Siemens
- DATE
- july 2009
- PROJECT ACCEPTED BY
- Jens Grunwald, Oliver Sawodni
Modification of Hydrogen analyzer system on all Units. Assembling cable traces, pulling and connecting cables, building frames and mounting connection boxes.
CONTRACTOR
Siemens
DATE
july 2009
PROJECT ACCEPTED BY
Jens Grunwald, Oliver Sawodni
CONTRACTORS’ EVALUATION
The project is completed according to the assignment without any remarks.
- CONTACTOR'S EVALUATION
- The project is completed according to the assignment without any remarks.