Trace Heating System for level measurement
in boiler drums in TPP “ENEL Maritsa East” 3
- CONTRACTOR
- Siemens
- DATE
- june 2009
- PROJECT ACCEPTED BY
- Jens Grunwald, Oliver Sawodni
Complete installation of Trace Heating System for level measurement in boiler drums. Assembling cable traces, pulling and connecting cables, building frames and mounting connection boxes.
CONTRACTOR
Siemens
DATE
june 2009
PROJECT ACCEPTED BY
Jens Grunwald, Oliver Sawodni
CONTRACTORS’ EVALUATION
The project is completed according to the assignment without any remarks.
- CONTACTOR'S EVALUATION
- The project is completed according to the assignment without any remarks.